How LAC tension is delaying work on Mumbai coastal road

Representative image

MUMBAI: It will take two months to assemble the tunnel boring machine (TBM) components at the coastal road work site at Priyadarshini Park in the city. BMC officials say that unless Chinese engineers are allowed to work on the machine, the project will suffer delays.
“Around 100 pieces of the TBM, imported from China, need to be put together. Because of India-China tensions, contractor L&T has been unable to get clearances for engineers from the Chinese manufacturer to reach Mumbai for the work. But Chinese engineers already working on the TBMs being used in Metro 3 and the Bangalore Metro can help assemble the coastal road TBM, the biggest in India, as the Metro TBMs are similar machines, size being the only difference,” said a BMC official.
“After the machine is assembled, we need to test it to start the actual work. But even for that we need engineers from the Chinese company that manufactured the machine. It was tested in China in December 2019, before being dismantled for shipping to India, but a test needs to be done again Read More – Source

[contf]
[contfnew]

times of india

[contfnewc]
[contfnewc]

Related Articles

Asia

Joshua Wong and fellow activists plead guilty in Hong Kong protests trial

bbc– Hong Kong democracy activist Joshua Wong and two fellow campaigners are...

Asia

Works worth Rs 1,559 cr completed in Bihar out of PM s package of Rs 1.25 lakh cr: Congress

PATNA: Congress general secretary Randeep Surjewala on Tuesday claimed that works worth...

Asia

Ex-Trump fundraiser pleads guilty to illicit lobbying on 1MDB, China

WASHINGTON: A former top fundraiser for President Donald Trump pleaded guilty Tuesday...

Asia

Covid: Delhi more “open” than Mumbai

NEW DELHI: With Unlock 5.0 underway from October 15, more businesses and...